Turning siloed project cost data into one basis for bid decisions

A state-owned construction company decided which projects to bid on while its cost data sat in separate silos. A project cost history platform now gives project managers, quantity surveyors and marketing one view of how similar projects performed before they commit.

Service
Management reporting and data
Client
State-owned construction company
Status
Awaiting go-live
Result
Build complete, ready for data migration and go-live

The challenge

Every new project starts with a decision: is it worth taking? The answer should come from how similar projects performed in the past, but cost and project data sat in separate silos across the company. Because that data was hard to pull together, fields that needed historical figures were often left blank, and teams had to judge feasibility without the full picture. That made it possible to keep taking on project types that, over the last five years, had lost money rather than made it.

  • Data silosCost and project data lived in separate systems and teams.
  • Incomplete evaluationsFields that needed historical data were often left empty when a project was assessed.
  • Decisions without evidenceProject managers, quantity surveyors and marketing could not easily check whether a project type had been profitable.
  • Repeat lossesProject types that had lost money in recent years could be taken on again.

How we approached it

  1. InsightWe started from the decision, not the system. Project managers, quantity surveyors and marketing needed one question answered: based on past projects, is this one worth taking? The data to answer it already existed, but it was locked in silos.
  2. DesignWe built data ingestion first, bringing past project and cost data together into one source. On top of it, the platform offers a seven-level drill-down through the work breakdown structure, so teams can see where costs and margins came from in similar projects.
  3. ImpactThe full system is built, beyond a proof of concept, and approved by finance and the business division. Once final sign-off is in, the remaining step is migrating project data and going live, with AI forecasting planned as a next phase.

What changed

  • Full system build completed, beyond a proof of concept
  • Project cost data structured for drill-down across the work breakdown structure
  • Ready for data migration and go-live after final sign-off

Client name withheld for confidentiality.